Week 27
Work Completed Week of June 7:
Early in the week the crew focused water main connections at various locations to piece the new water main in Spring Street to existing water mains at various locations. JMC connected the new 16” water main to the existing 16” along Webster Ave., connected the new 12” water main to the existing 12” along SW Clay Ave and installed 6” water main and a fire hydrant in Webster.
The remainder of the week focused on the remaining storm sewer work including removal of the existing storm sewer and manhole structure at the Webster intersection and installation of several catch basins and manholes in the Webster Ave. intersection.
Above: 16-inch water main connection at Webster Avenue
Above: Lead connection from 16-inch valve and hydrant installation.
Above: Storm sewer construction in the Webster intersection.
Upcoming the Week of June 14:
The Contractor will finish all remaining utility work early in the week and turn focus to building the roadway.