Week 31 Update
Work Completed the Week of July 5th:
During the short 4th of July week, JMC fine graded the aggregate base course in preparation of base paving on Wednesday. They also began excavating for sidewalk along Spring Street. On Wednesday, API was on site to pave the base course of asphalt along the entire stretch of Spring Street. The remainder of the week was spent adjusting castings and water valve boxes up to grade in preparation of final top course paving.
Above: Fine grading the aggregate base in preparation of base asphalt paving.
Above: Completed fine grading and start of paving operations.
Above: Base paving completed and adjusting drainage structures and valve boxes for final paving.
Upcoming the Week of July 12:
JMC will work on restoration. It is uncertain if the concrete crews will be on-site next week to finish concrete sidewalks and driveway approaches. Once that work is completed the roadway can be top course paved and pavement markings added. We will provide an estimated open to traffic date soon.