August 8th Update
The Contractor is waiting on a water quality structure to be delivered before work can begin on Pine Street. While they await delivery of that structure, the Contractor will be moving over to several isolated areas this week which include the following:
- The area of Rhoda Street installing an underground leaching system (Sheet 10)
- Coles Park Street performing routine catch basin cleaning and maintenance (Sheet 9)
- Margaret Avenue (at eastern terminus) to install an underground leaching system (Sheet 9)
- Lane Street to install an underground leaching system (Sheet 3)
- Laura Street to install in underground leaching system on the southern end and storm sewer system on the northern end (Sheet 3 and portions of Sheet 4)
Disruptions in these areas will only last a few days. The construction drawings can be accessed from an earlier post titled ‘Construction Drawings’.
The Contractor intends to move back over to Pine Street following the aforementioned work to being storm sewer work at that location.