Week 1
Work done the week of 8/17/2020:
Jackson Merkey Contractors, Inc. (JMC), had dewatering equipment placed and began work by setting a manhole near the County Pump Station. They will later have to come back to this location to make improvements to the metering pit although this later work should not have any traffic impacts associated with it. New 30-inch PVC sanitary sewer was placed across SB Shoreline Drive and into the median. Once across the SB lanes, JMC began back filling and compacting in an effort to reconstruct the roadway.
Work upcoming the week of 8/24/2020:
The Contractor intends to have the concrete curb and gutter placed Tuesday morning. Asphalt paving will take place on both Wednesday and Thursday. The intention is to have the SB lanes open to traffic on Friday.
The Contractor will immediately close and detour the NB Shoreline Drive lanes on Friday as well in order to extend the sanitary sewer easterly towards Yuba Drive the following week. The detour route will be the same as SB in the reverse orientation utilizing Terrace Street to Muskegon Avenue (Moses J. Jones Parkway). A map depicting the route will be posted later this week.