Week 10

Week of October 19:

Utility construction on Yuba Street continues.  The 27-inch sanitary sewer is being installed towards Spring Street where the connection to the existing trunk sewer will take place allowing sewerage flow to be re-routed through the new sanitary sewer.  Storm sewer and water main main improvements are also being done concurrently on Yuba Street.

              

 

             

Upcoming Week of October 26:

Sanitary sewer construction is expected to be fully complete on Yuba Street and crews will turn their attention to rebuilding the roadway.  Aggregate base material will be placed above the sand subbase with curb and gutter being extended throughout the project limits prior to asphalt paving.