Week 11

Week of October 26:

The sanitary sewer work has been completed in Yuba Street with the connection to the existing trunk sewer in Spring Street being made early in the week.  The installation required very deep cuts of 15-20 feet below grade.  The sewer flow that originally continued down Spring Street has now successfully been re-routed down Yuba Street.  The crews turned their attention to rebuilding the roadway the remainder of the week.

         

          

Upcoming Week of November 2:

Crews will continue to fine grade the roadway and place aggregate base course in preparations for concrete curb and gutter and asphalt pavement which is expected in mid-November.

As there is still considerable work left to be completed on Spring Street and the construction season is closing in, the project team has made the decision to postpone the remainder of the work on Spring Street from Muskegon Avenue to Western Avenue until the Spring of 2021 to ensure that work can be completed in adequate weather conditions.  At this time, the plan is to leave the surcharge material in place on Spring Street between Pine and Clay for the winter and will continue to be closed to thru traffic.  However, the intersection of Clay Street and Spring Street will be re-opened to allow easy access to United Way.