Week 12

Week of November 2:

Storm sewer and water main were constructed at the intersection of Spring Street and Yuba Street.  The water main was pressure tested and disinfected.  The connections to the existing water main will take place after the bacterial testing has come back acceptable which should be next week.

The roadway on Yuba Street was fine graded in preparation for curb and gutter and asphalt.  The concrete company was on site Friday morning to place curb and gutter along the entire stretch of roadway.

          

           

 

           

 

Week of November 9:

Crews from JMC will complete the water main connections at the intersection of Spring Street and Yuba Street.  Base course of asphalt paving is scheduled for Wednesday on Yuba Street.  Remaining concrete work, including minor curb and gutter, sidewalk, and driveway approaches will take place on Yuba Street, and a small location on Pine Street, later in the week.  Lawn Restoration in the parkway is also on-going.

Once the base course of paving is complete, JMC will raise castings on manhole structures in preparation for top course paving.  The final course of paving is tentatively scheduled for early in the week of November 16.