Week 13
Week 13 Update:
Work continues on Yuba Street as they look to fully complete the roadway prior to the Thanksgiving holiday. After successfully passing testing requirements on the water main, the connection to the existing 8-inch water main was constructed in Spring Street near Yuba Street. Concrete sidewalk and ADA sidewalk ramps were placed early in the week along Yuba Street. The roadway was fine graded and the base course of asphalt paving was placed towards the end of the week as the roadway starts to come together.
Upcoming the Week of November 16:
The contractor will be adjusting castings in the roadway up to final pavement grade, working on parkway restoration, and placing the final top course of asphalt pavement. The intent is to have Yuba Street open to traffic prior to the Thanksgiving holiday.