Lansing: 517-887-1100  Grand Haven: 616-743-7070

Week 2

Work done the week of 8/24/2020:

The Contractor extended the new 30-inch sanitary sewer across the SB lanes of Shoreline Drive and set a new manhole structure in the median.  Once that work was completed, attention turned to restoring the roadway to allow for thru traffic.  Concrete curb and gutter, aggregate base, two days of paving, and temporary pavement marking work was completed by the end of the day Thursday allowing the roadway to be open to traffic Friday morning.  Concurrently with the opening of the SB lanes, the NB lanes of Shoreline Drive were closed and detoured to allow continued construction of the new sanitary sewer towards Yuba Street.  The Contractor began pavement and curb removals Friday in the NB lanes and will resume sewer construction Monday morning.

Work upcoming the week of 8/31/2020:

Sanitary sewer will be extended across the NB lanes of Shoreline Drive during the early part of the week.  The Contractor will begin to rebuild the roadway on Wednesday and prepare it for concrete curb and gutter, aggregate base placement, and the first course of asphalt paving by the end of the week.  The NB lanes of Shoreline Drive are not expected to be open to traffic prior to the Labor Day weekend.  The short detour route from Terrace Street to Muskegon Avenue is currently not causing significant delays.  Alternative routes around the work zone are also available.