Lansing: 517-887-1100  Grand Haven: 616-743-7070

Week 22

Week 22 Update:

The crew continued laying 16″ water main and 8″ sanitary sewer near Webster Street.  The 8-inch sanitary was constructed up the hill towards Muskegon Avenue to service the properties south of Spring Street.  To date, approximately 95% of the sanitary sewer is in the ground with just a short stretch remaining to the south on Webster Street and then only testing will remain.  The Contractor must perform mandrel testing 30-days after placement to ensure the sewer has kept its circular form and capacity as well as pressure testing to ensure no leakage or infiltration.

The storm sewer work at Webster Street has been slow-going due to the current water levels in Ryerson Creek.  Although considerably better than last year, the water levels have presented problems with the pumps and dewatering equipment being able to keep up.  The Contractor was able to get the furthest downstream storm manhole installed this past week.

Crews also continued removals of the existing concrete box sewer which has been quite the process due to how it was originally constructed.  The 1-inch rebar utilized in the box must be sawcut to adequately break the sewer into sections so that it can be removed from the site.  As mentioned in previous updates, the box sewer was sitting on timber piles which kept the sewer in place as the roadway settled above it.

           

Above:  16″ water main and 8-inch sanitary sewer construction near Webster Ave.

           

Above:  8-inch sanitary sewer construction from Webster Ave. towards Muskegon Ave.

           

Above:  Storm manhole construction and battling the high water levels in Ryerson Creek.

           

Above:  Removal of the existing box sewer utilizing a jackhammer on the excavator.

            

Above:  Existing timber piles in-place which were utilized to stabilize the box sewer.  Sewer removal debris from the existing concrete box sewer.

Upcoming Week of May 10:

Crews will continue to remove the existing concrete box sewer from Spring Street.  The last of the 8-inch sanitary sewer will be placed south on Webster Street.  Water Main and storm sewer work is also anticipated to be completed in the Webster Ave. intersection and moving towards Muskegon Avenue.