The Contractor extended 30-inch sanitary sewer across the NB lanes of Shoreline Drive and quickly rebuilt the roadway in preparation for concrete curb and gutter and asphalt paving.  The concrete curb and gutter was placed on Wednesday.  Thursday morning the base course of asphalt was placed with the leveling course placed in the afternoon.  The top course of paving was placed on Friday morning and the roadway was opened to traffic shortly after noon for the long Labor Day weekend.  We thank the Contractor for moving swiftly to get the roadway opened up for the holiday weekend!

                   

Week of September 7

The Contractor will continue to move easterly towards Yuba Street with 30-inch PVC storm sewer.  Muskegon Avenue (Moses J. Jones Parkway) and Yuba Street will be closed for the roadway crossing and utility work beginning Tuesday morning.  Muskegon Avenue will be closed to through traffic for approximately a week and half and Yuba Street will have an extended closure for sanitary sewer, storm sewer, water main, and roadway reconstruction work.