Week of October 5:
Restoration continued on Pine Street, Western Avenue, and the cross lot parking lot between Pine & Terrace. Concrete work including flat work and curb and gutter was completed the previous weekend. The roadways and parking lots received aggregate base course and were fine graded in preparation of asphalt base course and top course. The roadways were open to traffic on Monday, October 12. The crew will continue with final lawn restoration, minor concrete work, and pavement markings with the roadway open to traffic.
The crew on Yuba Street continued with 27-inch sanitary sewer construction. Groundwater was persistent in the location of Cedar Street which reduced productivity, along with the crossing of a large diameter storm sewer and a planned water main relocation. Additional well points were placed to assist with dewatering as crews continued to place the sewer towards Spring Street.
Fair Street was also opened to traffic following top course paving on Saturday as required for the Bourdon-Addison alley sewer replacement.
Upcoming the Week of October 12:
Crews on Yuba Street will continue with sanitary sewer as well as water main and storm sewer. The water main relocation at Cedar Street will be done this week, tested, and placed back into operation towards the end of the week. Once the underground utility work is completed, attention will shift to re-building the roadway with concrete curb and gutter, aggregate base, and asphalt paving. We anticipate Yuba Street will be closed for approximately 3 more weeks.
Pine Street and Western Avenue will remain open to traffic although crews will be in the area conducting restoration and cleanup items.